The QCLNG Project involves construction of a world-class liquefied
natural gas (LNG) plant on Curtis Island off Gladstone in central
Queensland.
SMP Engineering was engaged to supply a team to drive the
practical completion of piping works and deliver completed system
packages for the client on the Ruby Jo and Glendower projects.
Key deliverables included a full review of ‘as built’ against piping
isometrics and P&ID’s (piping and instrumentation diagram)
drawings, identifying gaps and providing yellow and red line mark
up. Discrepancies were reviewed against TQ’s (technical queries)
and redline mark-up completed. On completion of system packages,
pipelines were walked down with the client representatives for
acceptance. SMP’s team of engineers were also involved in
identifying and closing out of punch list items.
Project Key Facts
Project Owner
Queensland Gas Company
Project
QCLNG Upstream Project
Client
Thiess Pty Ltd
Value
~$1.8 Billion
SMP Scope
Engineering team providing
engineering and supervision to
support the practical completion of
the project.
Project Scope
+ As-builts delivered in a manner
to align with greenfield
construction
+ Over 1000 isometric drawings
+ Install flange management tags
+ Zero incidents
+ Environmental incident free
+ Seamless integration with client
team
+ Procurement and supply chain
management support
Testimonial
“SMP provided a quality team of engineers to assist us to drive mechanical and practical completion